Edit Capital Planning Project

When more information about a CIP project is known, this information can be added to existing projects within the CIP Project layers using the Cost Estimating toolbar.

To edit a CIP Project, complete the following steps:

  1. Open the Water Utility Capital Planning map.
  2. Open the Project Cost Estimating Window button on the Cost Estimating toolbar and dock within the map document.
  3. Click the Select and Load Existing Project button in the Project Cost Estimating window and choose a project in the map. This project is then added to the Project Cost Estimating window.
  4. Click the Start Editing the CIP Layers Workspace button in the Project Cost Estimate window to change existing assets or project details.
  5. New assets can be sketched or existing assets can be added to this project by using the Sketch New Asset tool or selecting an existing asset.
  6. Click Save Selected Assets to a Project to save any new features to the CIP Projects layers.
  7. When all asset and project detail information is added, click Save Edits within the Project Cost Estimating window.
  8. Click the Stop Editing the CIP Layers Workspace button within the Project Cost Estimating window to end the editing session.
  9. The project and assets can now be viewed with estimated cost within the CIP Projects layers.
Top